Sirajganj (NWPGCL) Power Plant (Unit-1)
Basic Information
- Name of the Power Plant: Sirajganj Power Plant
- Location:
- Geographic Position:
- Capacity: 414 Megawatt
- Fuel:
- Technology: Combined Cycle Power Plant (CCPP)
- PPA Lifetime:
- Land Acquisition: Undisclosed
- ESF Category: A (according to ADB and World Bank Safeguard Policies)
- Industrial Category: Red (according to Bangladesh Environmental Protection Rule 1997)
Executing Agencies
- Implementer:
- Sponsor:
- Power Purchaser:
- Financier:
- Insurance Company: Undisclosed
- EPC Contractor: SEPCO III (Subsidiary of Power China Resources)
- O&M Contractor:
- Technology Supplier:
- ESIA Consultant: Undisclosed
Finance Information
- Total Budget: Undisclosed
Important Dates
- COD Operation: 19 March 2019