Basic Information
- Name of the Power Plant: Bhola Integrated Power Plant (Bhola IPP) or Bhola II
- Location: Kutba Union, Burhanuddin Upazila, Bhola District, Bangladesh
- Capacity: 220 - 225 Megawatt
- Category: Combined Cycle Power Plant (CCPP)
- Fuel: Natural Gas and High Speed Diesel (HSD)
- Land Acquisition: 28.28 Acres (22.00 Acres from Bhola I Project, 5.78 Acres from Local People and 5.5 Acres for Gas pipline)
- PPA Period: 23 Years
- ESF Risk Category: B (according to AIIB Environment and Social Framework)
- Industrial Category: Red (according to the Environmental Protection Act of Bangladesh)
Executing Agencies
- Executing Company(s): Nutan Bidyut (Bangladesh) Limited (NBBL), a subsidiary of Shapoorji Pallonji Infrastructure Capital Limited (SP Infra)
- Sponsor Company(s): Shapoorji Pallonji Infrastructure Capital Company Limited (SP Infra), a subsidiary company of Shapoorji Pallonji (SP) Group, Mumbai, India
- Financing Company(s): Asian Infrastructure Investment Bank (AIIB), Infrastructure Development Company Limited (IDCOL), Islamic Development Bank (ISDB)
- EPC Contractor(s): Bisho Infra Projects Limited (BIPL), a project of Shapoorji Pallonji Group of Companies (SP Group) and Global Infra FZCO (10% owned by Shapoorji Pallonji and Company Private Limited (SPCPL) and 90% owned by Global Energy Ventures Mauritius (GEVM))
- Technology Supplier: General Electric, USA
- Insurance Company(s): Undisclosed
- ESIA Consultant(s): ERM India Limited
- IR Audit Report: AECOM India Private Limited
Financial Information
- Total Budget: USD 271.90 Million
- AIIB Investment: USD 60.00 Million (22.1%)
- IDCOL Investment: USD 22.3 million (up to 2018: 8.2%)
- ISDB Investment: USD 60 Million (22.1%)
- SP Infra Investment: USD 129.60 Million (47.7%)
Important Dates
- Establishment of NBBL: 27 March 2016
- Letter of Intent from BPDB: 18 April 2016
- IEE Report Submitted to DOE: 23 October 2016
- ESIA Report Approved by DOE: 20 April 2017
- ESIA Final Report Released: January 2018
- Land Acquisition (1st Phase): January 2017
- Land Acquisition (2nd Phase): December 2018
- Land Acquisition (3rd Phase): January 2019
- Land Acquisition (4th Phase): April 2019
- AIIB Board Approval: 9 February 2018
- ISDB Loan Agreement: 26 May 2018
Project Related Documents
- Project Summery Information (PSI)
- Environmental & Social Impact Assessment (ESIA)
- Environmental & Social Impact Assessment Report (ESIA): Updated
- ESIA Annexure
- Annexures to the Final ESIA Report
- Environmental Monitoring Program (EMP)
- Environmental & Social Action Plan (ESAP)
- EIA Approval from Department of Environment
- ESIA Summery: Bhola II (Bengali)
- Grievance Redressal Mechanism (Bengali)
- Involuntary Resettlement Audit Report
Monitoring Reports
- Mehedi, H., Tuhin, S.A. and Prince, M.A. (2018). Bhola Integrated Power Plant (Bhola IPP) and its Impact on Local Communities: Voices from the Ground: A Civil Society Study Report. CLEAN (Coastal Livelihood and Environmental Action Network). Khulna, September 2018.
- BIC Europe (2019). Dangerous Distractions: Why the Asian Infrastructure Investment Bank must help turn the tide on fossil fuels in Bangladesh. Bank Information Center (BIC) Europe, Coastal Livelihood and Environmental Action Net-work (CLEAN) and NGO Forum on ADB, Amsterdam: July 2019
Media Clippings
- 11 Jul 2019: AIIB must stop backing gas in climate-hit Bangladesh: Climate Home News
- 25 Mar 2019: Bangladesh Bhola power project tests AIIB promises: The Third Pole
- 28 Jan 2019: BRAC Bank, Bishwo Infra Projects ink deal: The Daily Sun
- 27 Jan 2019: BRAC Bank signs agreement with Bishwo Infra Projects: The Financial Express
- 09 May 2018: GE Power achieves another milestone in Bangladesh: MAX Group’s 163MW combined-cycle power plant begins commercial operation: GE Imagination
- 04 Mar 2018: AIIB Invests to Help Bangladesh Address Power Shortages: Modern Diplomacy
- 28 Feb 2018: AIIB approves loan for Bangladesh Bhola IPP energy project: Power Technology
- 27 Feb 2018: AIIB to give $60m for 220-MW plant in Bhola - Its total loan for BD to reach $285m: The Financial Express
- 02 Nov 2017: New CCGT in Bhola, Bangladesh, will be GE 6F.03 fleet leader: Modern Power Systems
- 19 Sep 2017: GE to Supply Equipment for Shapoorji Pallonji Group's Combined Cycle Power Plant, Bangladesh: Mining Connection
- 17 Sep 2017: GE Power to provide equipment for 220MW Bhola plant: The Daily Star
- 15 Sep 2017: GE Power bags order from Shapoorji Pallonji Group - Report: MoneyWorks4me
- 14 Sep 2017: GE Power to supply gear for Bangladesh plant: Business Line
- 13 Sep 2017: GE Power bags SP Group contract for power plant in Bangladesh: The Economic Times
- 13 Sep 2017: General Electric Wins Contract from Shapoorji Pallonji Group to Supply Equipment for a Power Plant in the Bhola District: Benzinga
- 29 Aug 2017: First power plant fully funded by India to be set up in Bhola: The Dhaka Tribune
- 28 Aug 2017: Indian co gets 220MW power plant deal sans bidding: Daily NewAge
- 28 Aug 2017: Indian co gets 220MW power plant deal sans bidding: Pakistan Defence
- 28 Aug 2017: Europeans increasingly interested to invest in power sector - Nasrul Hamid: United News Bureau (UNB)
- 28 Aug 2017: BPDB signs agreement with Indian company to buy 220 MW power: Energynewsbd
- 28 Aug 2017: Shapoorji Pallonji Group Bags Power Supply Deal: Energy & Power Bangladesh
- 13 Sep 2016: GE Power to Supply Equipment for 200-MW Plant in Bangladesh: Power Engineering
- 17 Mar 2016: Six power deals get go-ahead - Govt goes for wholesale unsolicited power deals; special act being used for 'speedy deals' on 2-yr-old proposals: The Daily Star
- 07 Mar 2016: New Power Plant in Bhola: Unsolicited deal for Indian company?: The Daily Star
- 24 Aug 2015: Shapoorji Pallonji to set up a 225 MW dual-fuel power plant in Bangladesh: CoalPost
- 03 July 2015: 225 MW Power Project in Bhola: Indian Shapoorji to relocate its installed plant: Daily NewAge
- 16 Sep 2012: India's Lanco to set up Bangladesh's Bhola Power Plant: Asian Power
- Undated: Thermal Power Plant - CCPP Bhola: Shapoorji Pallonji Infrastructure
Contact Persons
- Jagannath Sinhamahapatra, Director, Nutan Bidyut Bangladesh Limited (NBBL), B&B Empire, 7th Floor, Plot no.116, Block E, Banani, Dhaka - 1213, Bangladesh. Tel: +88-02-9890055; Email: j.sinhamahapatra@nutanbidyut.com
- Mitesh Soni, General Manager, Shapoorji Pallonji Infrastructure Capital Company Private Limited, 41/44, Minoo Desai Marg, Colaba, Mumbai - 400005, Maharashtra, India. Tel: +91-22-67490186; Fax: +91-22-67490017; Email: mitesh.soni@shapoorji.com
- Prakash Bajoria, Project Team Leader (Private Sector Investment Operations Specialist), Asian Infrastructure Investment Bank, B-9 Financial St., Xicheng District, Beijing, China 100033. Tel: +86-10-83580145; Fax: +86-10-83580909; Email: prakash.bajoria@aiib.org