Summit Meghnaghat Power Plant II

Basic Information

  1. Name of the Power Plant: Summit Meghnaghat Power Plant II 
  2. Location: Meghnaghat, Naryanganj 
  3. Capacity: 305-335 Megawatt 
  4. Fuel: Dual Fuel (HFO/LNG)
  5. Technology: Combined Cycle Power Plant (CCPP)

Executing Agencies

  1. Executing Companies: Summit Meghnaghat Power Company Limited (SMPCL) 
  2. Sponsor Companies: Summit Industrial and Mercantile Corporation Ltd. 
  3. Financing Companies: International Finance Corporation (IFC), Infrastructure Development Company Limited (IDCOL) 
  4. Insurance Company
  5. EPC Contractor
  6. Technology Supplier: General Electric
  7. ESIA Consultant:

Finance Information

  1. Total Budget: Undisclosed
  2. IDCOL Investment: USD 30 million
  3. IFC Investment: Undisclosed
  4. Summit Investment: Undisclosed

Important Dates

  1. August 2014: IDCOL approved a loan of USD 30 million

Media Clippings

  1. 3 Nov 2010: Summit makes winning offer for Meghnaghat-II: The Daily Star